Construction Milestones

March 2012

Landscaping

August 2011

Minor works, paving and fencing to complete substation

September 2010

Electrical and mechanical installation started

September 2010

Phase One civil construction works completed

July to October 2010

North Wall construction commenced (installation of steel and precast concrete panels)

July 2010

Control room construction substantially complete

December 2009

Access roads completed

2008

Local electricity network diverted slightly to enable substation connection

Spring 2009

Most pre-construction surveys completed

Autumn 2009

Earthworks and screening mounds completed

July to October 2010

Transformer deliveries

November 2010

November 2010

March 2011

Phase Two civil works started

October 2011

Substation commissioning

October 2012

Construction complete